EdgeConnex Amsterdam
Data CentreClient
EdgeConnex
Architect
Gensler
Project Manager
BCEI
Main Contractor
Winthrop
Civil Structural Engineers
Pinnacle
First Q Partner
Smiths van Burgst
Project Size
20 MW
Project Status
Construction
Project Description
This consists of 2 units of 10MW COLOs and associated electrical support rooms (electrical rooms, MDF rooms, MV rooms, etc.).
Ethos Input
As part of the mechanical and electrical deliverables Ethos Engineering were commissioned to provide the design through BIM, and Revit MEP was used for this project. The M&E services were developed to LOD 300 and transferred over to the main contractor to complete throughout the project.
Ethos Engineering provided full electrical design services and construction administration support.
Unique / Key Features
The electrical support rooms are fully prefabricated pods which were manufactured off site and positioned externally to the building to facilitate an accelerated construction programme.
The cooling was achieved by an all-air cooling system, utilising air side economisers (outside air) to cool the server spaces.
The project also involved infrastructure extension and resilience, in relation to site MV supplies and connection to other telecoms infrastructure.
Worked closely with our Dutch First Q Partner – Smits van Burgst - to ensure local compliance, and offering a contact on the ground who was available to the client while managing the entire design process from our Dublin offices.